How long does a kitchen remodel take?

Most of our kitchen remodels take four to six weeks on site. Here is how a typical five-week job runs.

Week by week

  1. Week 1: strip-out, any wall changes and first-fix plumbing
  2. Week 2: electrics, plastering and drying
  3. Week 3: cabinets and worktop templates
  4. Week 4: worktops, tiling and splashbacks
  5. Week 5: appliances, paint and handover

Order the worktops early: they are the part that most often runs late. Aisha, interiors project lead