Most of our kitchen remodels take four to six weeks on site. Here is how a typical five-week job runs.
Week by week
- Week 1: strip-out, any wall changes and first-fix plumbing
- Week 2: electrics, plastering and drying
- Week 3: cabinets and worktop templates
- Week 4: worktops, tiling and splashbacks
- Week 5: appliances, paint and handover
Order the worktops early: they are the part that most often runs late. Aisha, interiors project lead